The government is targeting January 2027 to secure full financing for the Shs12.31 trillion Standard Gauge Railway (SGR) project, paving the way for major construction works to begin nearly two years after President Yoweri Museveni launched the project. 

Works and Transport Minister Fred Byamukama told Parliament on Tuesday that the four-year construction period for the 272-kilometre Malaba-Kampala railway line has not yet commenced because the Government is still mobilising funds and addressing conditions set by prospective lenders. 

Although the project was officially launched in November 2024, Turkish contractor Yapi Merkezi has so far undertaken preliminary activities under a limited notice to proceed arrangement. Byamukama said the Government was working towards financial closure in January 2027, after which it expects to issue the full Notice to Proceed in early 2027, allowing the contractor to embark on the main construction works.

The project contract, signed on October 14, 2024, between the Government and Yapi Merkezi-YM Global joint venture, is valued at approximately 2.702 billion Euros (about Shs12.31 trillion).

The latest financing target comes after years of delays that have stalled Uganda’s plans to establish a modern railway network linking the country to regional trade routes. In 2015, the Government agreed with China Harbour Engineering Company (CHEC) to construct the Malaba-Kampala railway line, with the Chinese firm expected to facilitate financing from China. 

However, the arrangement collapsed after years of unsuccessful negotiations with China Exim Bank, which had not committed the anticipated financing. The government subsequently terminated the agreement and turned to Turkey’s Yapi Merkezi, signing a new construction contract in October 2024.

Government plans to finance the current project through a combination of export credit agencies, development finance institutions and its own contribution.

Export credit agencies are expected to provide 58 per cent of the funding, development finance institutions 25 per cent, while the Government will contribute the remaining 17 per cent. The Islamic Development Bank (IsDB) approved 650.75 million Euros (about Shs2.96 trillion) for the project in June 2026. The financing will support major infrastructure components, including the 553-metre Jinja Nile Bridge, a 2.12-kilometre tunnel between Mbuya and Kampala, six railway stations and three workshops.

The OPEC Fund for International Development has also completed its appraisal processes for the project, while negotiations with export credit agencies are ongoing. The OPEC Fund has been considering a 150-million-Euro loan, with its appraisal covering project designs, implementation arrangements, disbursement schedules and environmental and social safeguards. 

Government is also pursuing a Sukuk arrangement to mobilise its contribution towards the project. Byamukama said the financing process is expected to be concluded after outstanding lender appraisals, environmental and social requirements and other conditions required by financiers have been addressed.

Meanwhile, the Government has completed preliminary works worth 75 million Euros (about Shs341.63 billion), undertaken by Yapi Merkezi under a Limited Notice to Proceed issued in May 2025. The works, which commenced on May 14, 2025, and were completed in October 2026, included surveys, geotechnical investigations, preliminary and selected detailed designs, utility identification and the establishment of construction support facilities.

These include a construction camp, batching plant, precast yard, sleeper factory and laboratory in Iganga, as well as procurement of essential construction equipment, including earthmoving machinery. Byamukama said the preparatory activities had reduced technical uncertainties and established the capacity required to transition into full construction.

However, land acquisition remains another major challenge, with the Government yet to compensate all people affected by the railway corridor. According to the minister, the 272-kilometre route requires 3,536.26 acres and affects approximately 12,946 people. The government has so far compensated 7,721 project-affected persons, covering 2,108.93 acres, equivalent to about 60 per cent of the required land.

The compensation requirement stands at Shs845.52 billion, of which Shs373.07 billion has been paid, leaving an outstanding balance of approximately Shs472.45 billion. Byamukama said land acquisition was most advanced between Malaba and Mayuge, where about 98 per cent of a continuous railway corridor has been secured. He told Parliament that Government had so far secured approximately 130 kilometres of corridor where the contractor could begin construction.

Government has allocated Shs221 billion for compensation in the 2026/2027 financial year and is engaging the Ministry of Finance, Planning and Economic Development to secure additional resources. Beyond land acquisition and financing, the Ministry is coordinating with the Ministry of Energy and Mineral Development and the Uganda Electricity Transmission Company Limited to establish the 25-kilovolt electric traction supply system, including grid connections, substations and transmission-line extensions.

Government is also working with Uganda Railways Corporation, Kenya, and development partners on cross-border interoperability, railway operations, staffing, maintenance, safety and asset management. The Malaba-Kampala railway line is intended to connect Uganda to Kenya’s existing Standard Gauge Railway network and the Port of Mombasa, providing a more efficient transport route for imports and exports.

The project is expected to reduce reliance on road transport, improve cargo movement and strengthen Uganda’s access to regional and international markets. It also forms part of the Government’s wider plan to establish an approximately 1,697-kilometre railway network connecting Uganda to neighbouring countries.

Preparatory studies are progressing for the Northern Route, approximately 762 kilometres, towards South Sudan and the Democratic Republic of Congo, as well as the Western and Southern routes, covering approximately 663 kilometres towards the Democratic Republic of Congo and Rwanda.  The planned railway and lake-port connections are also expected to support links with the Central Corridor and the Port of Dar es Salaam. Despite the November 2024 launch, the Government has not yet provided a definitive calendar completion date for the Malaba-Kampala line because the contractual four-year construction period is tied to the effective commencement of the main works.

Byamukama said Government’s immediate priorities include completing outstanding lender appraisals and environmental and social requirements by December 2026, continuing compensation of affected persons, concluding financing arrangements and finalising utility, traction power and operational preparations. He said the Government remained committed to implementing the railway project and developing its regional connections, adding that the House would be updated as the remaining milestones are achieved.  

Kungu Al-Mahadi Adam, is a Ugandan journalist with over 10 years of experience in journalism and broadcasting. He has worked with several Ugandan media organisations, including NBS Television, Sanyuka...