As the country enters a season of potentially enhanced rainfall, unresolved defects at Isimba Hydropower Plant have renewed fears about the dam being flooded by excess water.

There is also concern that the contractor has done little to repair a spillway that engineers say cannot safely handle its full design capacity. 

Sources revealed that government officials led by Engineer Badiru Kiggundu and managers from Uganda Electricity Generation Company Limited (UEGCL) revisited the 183-megawatt plant on Friday to follow up on efforts to have China International Water and Electric Corporation (CIWE) rectify defects at the facility. 

Dr. Kiggundu, who leads the presidential Project Steering Committee (PSC) tasked with overseeing the completion, supervision, and remediation of structural defects, including concrete cracks and spillway erosion.   

The outcome of Friday’s inspection, including whether the contractor has agreed to a firm schedule for completing the outstanding work, was not immediately available. 

It was held behind closed doors for over five hours and could not be disclosed by the source, though he revealed that the parties are still concerned about the continuing erosion at the dam. 

Dr. Badiru Kiggundu did not respond when contacted by URN about the said meeting.   

The visit comes as the country prepares for increased rainfall and possible flooding during the October-December rainy season.

It also follows repeated warnings by UEGCL engineers that dama